Phase I : Completed a review of the promising practices in November 2018.
Completed Pilot Interviews in Brewton, AL in December 2018.
Presented a Preliminary report of our findings in our extensive literature review to Alabama Department of Child Abuse and Neglect Prevention (ADCANP) in February 2019.
Phase II : Submitted IRB on January 14, 2019.
Extension Agent orientation was completed in February 2019.
Received IRB approval on April 22, 2019.
Focus Group 1 was completed on May 13, 2019.
Focus Group 2 was completed on May 23, 2019.
Focus Group 3 was completed on May 30, 2019.
Focus Group 4 was completed on June 13, 2019.
Focus Group 5 was completed on June 18, 2019.
Focus Group 6 was completed on June 20, 2019.
Focus Group 7 was completed on June 25, 2019.
Focus Group 8 was completed on June 27, 2019.
Focus Group 9 was completed on July 11, 2019.
Focus Group 10 was completed on July 12, 2019.
Focus Group 11 was completed on July 18, 2019.
Focus Group 12 was completed on July 23, 2019.
Focus Group 13 was completed on July 24, 2019.
Focus Group 14 was completed on July 26, 2019.
Focus Group 15 was completed on July 30, 2019.